First phase of Grand Hogback Trails project at Rifle Arch nears completion

Chelsea Self / Post Independent A new trail system at Rifle Arch is nearing the completion of 6.3 miles of trail, according to a Rifle department head. Rifle City Planner Nathan Lindquist reported to the city council Feb. 3 that the first phase, which will likely cost $80,095, is scheduled for a spring completion. The second phase of the project includes the construction of a new parking lot, added signage and relocation of the existing hiking trail, among other improvements. The second phase is estimated to cost $113,097. In 2020, the city signed a contract with Gumption Trail Works to complete the first phase. Delays caused by Bureau of Land Management permitting issues, however, only allowed for 5.7 miles of trail to be completed before wintertime at $70,045, Lindquist said.