Thirty major road works start within a few days of each other in Marlborough stuff.co.nz - get the latest breaking news, showbiz & celebrity photos, sport news & rumours, viral videos and top stories from stuff.co.nz Daily Mail and Mail on Sunday newspapers.
Councils are scrambling to deal with holes in their roading budgets, after the Government transport agency warned it could not meet funding expectations.
Tuesday, 25 May 2021, 9:11 am
Critical infrastructure upgrades to wastewater,
stormwater and water mains in Muller Road are entering the
next stage.
The $3.4 million project, between Redwood
and Weld Streets, is part of Blenheim’s 30 year
infrastructure upgrade strategy. “The wastewater mains are
leaking and must be replaced and the Council will upgrade
and replace the stormwater and water supply piping at the
same time to ‘do it once and do it right’,” said the
Council’s Assets and Services Manager, Richard
Coningham.
Local contractor Fulton Hogan has been
engaged to undertake the works.
The water main works
have now been completed between Redwood and Scott Streets.
Eight months into the 18-month long northwest Blenheim sewer upgrade, work is progressing well, thanks to great support from the community. Contractors Schick Civil Construction have finished work in Fulton Street, where a 255m new gravity main has been installed .