Comments Before the Minnesota Public Utilities Commission In the Matter of a Commission Investigation into the Potential Role of Third-Party Aggregation of Retail Customers rstreet.org - get the latest breaking news, showbiz & celebrity photos, sport news & rumours, viral videos and top stories from rstreet.org Daily Mail and Mail on Sunday newspapers.
June was an interconnection milestone. On June 14, PJM Interconnection, L.L.C. (“PJM”) filed a “comprehensive reform” of the interconnection process set forth in its Open Access.
Request to Accept Late-Filed Comments and Post-Technical Conference Comments of the R Street Institute rstreet.org - get the latest breaking news, showbiz & celebrity photos, sport news & rumours, viral videos and top stories from rstreet.org Daily Mail and Mail on Sunday newspapers.
[co-author: Shawn Whites]
On January 19, 2021, the Federal Energy Regulatory Commission (FERC) directed the nation’s six Regional Transmission Organizations and Independent System Operators (RTOs/ISOs) to submit reports on the integration of “hybrid” generation plus energy storage resources in their markets.
1 FERC’s order asks RTOs/ISOs to provide input into their current practices and “any ongoing efforts to develop reforms” within four issue categories: (i) terminology (i.e., what constitutes a “hybrid resource”); (ii) interconnection (processes and requirements); (iii) market participation (including in wholesale energy, ancillary services and capacity markets); and (iv) capacity valuation.
2 RTO/ISO reports are due July 19, 2021, and interested parties may submit comments on the reports by August 18, 2021.