comparemela.com

Latest Breaking News On - Power service areas affected - Page 1 : comparemela.com

Scheduled power service interruptions on May 4 and 5

(Commonwealth Utilities Corp.) —  There will be scheduled power service interruptions on May 4 and 5, 2021, for customers in Papago.  The purpose of the scheduled power interruptions is for CUC to temporarily shut-off power in order for its linemen to safely replace existing rotted power poles to concrete poles in the affected areas.  Tuesday, May 4 • Outage Type: Sectionalized Interruption on the Feeder 4 Circuit  • Project Location: Papago • Power Service Areas Affected: o From 8:30 a.m. to 1:30 p.m. — Isa Drive, Papago (Ahgaga Dr. & Amot Ln.) o From 8:30 a.m. to 3:30 p.m. — Papago (parts of Isa Drive) • Water Well Affected: None • Wastewater Lift Station Affected: None

© 2024 Vimarsana

vimarsana © 2020. All Rights Reserved.