As Jacksonville eyes doubling its gas tax, residents are still waiting to see construction completed on major road work promised when City Council extended that same gas tax in 2014.
Most of the work on that list has either been done or is under way, but the Jacksonville Transportation Authority expects it will be 2024 before all the construction wraps up by closing out the final project in the northern end of San Pablo Road.
The original scope called for about $100 million of work but those estimates proved to be outdated and the tab has risen to around $167 million, which includes $13 million of JEA utility work added in to the projects.