NTPC jumped 4.08% to Rs 103.40 after the company informed about the successful completion of trial operation by Unit-2 of 800 MW capacity of Gadarwara Super Thermal Power Project.
In a BSE filing made during market hours today, the company said that based on achievement of approved norms, unit-2 of 800 MW capacity of Gadarwara Super Thermal Power Project has successfully completed trial operation and consequently included in the installed capacity of NTPC.
With this, the total installed capacity of NTPC and NTPC group has become 52,110 MW and 64,875 MW, respectively, it added.
NTPC is a Maharatna company operating in the power generation business. The principal business activity of the firm is electric power generation through coal based thermal power plants. It also engages in the business of generation of electricity from hydro and renewable energy sources.
tanmayFebruary 18, 2021 2
The Global Dodecene Market research report primarily aims to hint at opportunities and challenges in the Global industry. The report also underscores potential risks, threats, obstacles, and uncertainties in the market and helps clients in intuiting them precisely and operating their business accordingly. The report covers an extensive span of the global Dodecene market ranging from historical and current events to futuristic stich of the market. The report covers the post-COVID-19 (Corona Virus) impact on various regions and major countries and on the future development of the industry is pointed out.
Click the link to get a Sample Copy of the Report:
NTPC announced that consequent upon successful
commissioning, Unit-4 of 150 MW of Kameng Hydro-Electric Project (4x150 MW) of North Eastern
Electric Power Corporation (a wholly owned subsidiary company of NTPC ) has been
declared on commercial operation w.e.f. 00:00 Hrs. of 12 February 2021.
With this, the commissioned and commercial capacity of NTPC group has become 64075 MW.
Powered by Capital Market - Live News
(This story has not been edited by Business Standard staff and is auto-generated from a syndicated feed.) Dear Reader,
Business Standard has always strived hard to provide up-to-date information and commentary on developments that are of interest to you and have wider political and economic implications for the country and the world. Your encouragement and constant feedback on how to improve our offering have only made our resolve and commitment to these ideals stronger. Even during these difficult times arising out of Covid-19, we continue to remain committed t
Read more about Axis Bank, HUL, Infosys, NTPC in focus on Business Standard. Axis Bank s net profit tanked 36.45% to Rs 1116.60 crore while total income fell 1.13% at Rs 19,274.39 crore in Q3 December 2020 over Q3 December 2019. The private lender s PAT was adversely impacted by about Rs 1,050 crore on account of prudent
Read more about Market drops on weak global cues on Business Standard. Key benchmark indices are trading lower in early trade on weak global stocks. At 9:25 IST, the barometer index, the S&P BSE Sensex, was down 510.33 points or 1.08% at 46,899.60. The Nifty 50 index was down 136.20 points or 0.98% at 13,831.30.