The much-awaited underpass at Sector 51-52 and 71-72 intersection, which was planned to ease traffic from Wave City Centre metro station towards Noida Extension, will miss its December 2020 deadline.
NOIDA: The much-awaited underpass at Sector 51-52 and 71-72 intersection, which was planned to ease traffic from Wave City Centre metro station towards Noida Extension, will miss its December 2020 deadline. With over 80% of the work completed, it is now expected to be ready by January-end or early February next year.
Covid lockdown and the recent National Green Tribunal (NGT) regulations on construction activities, including slow digging to avoid dust pollution, have been cited as reasons behind the slow pace of work.