NAWALPARASI, May 1: A 33-kilometer stretch of the Narayanghat-Butwal section along the East West Highway has been blacktopped. Initially slated for completion within the deadline of 42 months, the project reports a 50 percent accomplishment in over five years and three months.
NAWALPUR, Dec 27: The task of blacktopping in the eastern section of the Narayanghat-Butwal road stretch along the East-West Highway has gained momentum.
KATHMANDU, Nov 24: The Asian Development Bank (ADB) project directorate has warned the contractor company of the Narayanghat-Butwal road section to terminate the contract if the overall physical progress of 50 percent is not achieved by December 2023.
MADHYABINDU (Nawalparasi), Oct 12: The eastern section of the Narayanghat-Butwal road expansion project has so far witnessed sluggish physical progress.