The National Works Agency (NWA) is reporting that work is going smoothly on the Mount Moriah to Bohemia Rehabilitation Project in St Ann. According to the NWA, just one month after the start of the work, the project is already 65 per cent complete and on track to be finished before the six-month mark. Since breaking ground for the project on February 13, this major road initiative, valued at $135.