TxDOT Atlanta District
Report Oct 16 - Oct 22
Bowie County I-30 – From FM 989 to AR State Line, reconstructing and widening the highway, concrete paving in median I-30 – From FM 989 to FM 3419, the extension of frontage roads I-30 – Westbound at Exit 207/Spur 594, ramp rehabilitation.
ATLANTA – Texas Department of Transportation (TxDOT) has scheduled a portion of US 80 in Upshur County to be resurfaced soon, according to plans approved in September.
“The project will extend from the Wood County line to 0.3 miles east of SH 155, an area covering almost three miles,” said Mount
Editor’s note: This is a schedule of work being planned for Sept. 18-24. Weather conditions and unforeseen problems can cause delays or cancellation of work.
Weekly Roadwork Report Atlanta
September 11 – September 17, 2022
Bowie County I-30 – From FM 989 to AR State Line, reconstructing and widening the highway, concrete paving in median I-30 – Westbound at Exit 207/Spur 594, ramp rehabilitation. Exit & entrance ramps are closed, wit