Kamoa-Kakula Shatters Previous Production Records, Mining 400,000 tonnes of ore Grading 5.36% Copper in March, Including 100,000 tonnes Grading 8.70% Copper from the Centre of the Kakula Mine
Pre-production ore stockpiles hold 2.56 million tonnes grading 4.60% copper, containing more than 117,000 tonnes of copperOverall progress of Kamoa-Kakula’s first phase, 3.8-Mtpa mining and milling operation 92% complete; commissioning of concentrator plant underway with first copper production on track for July 2021Kamoa-Kakula’s main 220-kV substation energized with clean, renewable hydropowerPhase 2 expansion to …
Pre-production ore stockpiles hold 2.56 million tonnes grading 4.60% copper, containing more than 117,000 tonnes of copper
Overall progress of Kamoa-Kakula’s first phase, 3.8-Mtpa mining and milling operation 92% complete; commissioning of concentrator plant underway with first copper production on track for July 2021