The site where Cargill plans to build their 12-track, 200-car rail yard, Nov. 27, 2019. Izabela Zaluska/Little Village
Cargill’s Cedar Rapids rail yard is expected to be operational by November, officials involved with the project shared during a virtual town hall meeting on Wednesday.
The meeting was scheduled by Cargill to give residents an update on the construction timeline and an opportunity to provide feedback on the design and placement of the sound berm, as well as tree and vegetation types.
The 12-track, 200-car rail yard will be built on city-owned property south of Stewart Road. Over the two years, plans have shifted back and forth between the Stewart Road property and the “farm property” on Otis Road. Both sites border the Rompot neighborhood and are near the Prairie Park Fishery.