A $283M gas power plant being built near Billings may face new environmental scrutiny as the state Supreme Court weighs a lower court decision that a state law barring greenhouse gas emission impact detail is unconstitutional.
Work is set to resume on the 175-MW Yellowstone County project, with Burns & McDonnell as EPC contractor, after new court ruling that followed revised state law banning regulators from weighing greenhouse gas emissions in permit reviews of new energy projects.