Electricity of Vietnam (EVN) fears that the electricity imports from Laos may face difficulties because of the limited capacity of the transmission system.
Business & Human Rights Resource Centre
Featured pages
Featured pages Update
Featured pages
Featured pages
China Southern Power Grid response on Namtha 1 Dam
China Southern Power Grid responded to the Resource Centre s request for comment. The company quoted a response from Nam Tha 1 Lao Power Company Limited, produced as follows:
Subject: Clarifications on the Report of the Namtha Hydro Project in Laos
[.] [A]fter a thorough investigation into the issues raised in the âLao Villagers Relocated from China-Backed Dam Lack Land to Grow Cropsâ article, we have concluded that the contents described in the article were seriously inconsistent with the actual situation. Our fact-based formal response and clarifications are as follows: