The UMass Amherst Police Department held a swearing-in and badge pinning ceremony for nine new officers and celebrated the promotion of a longtime member of the UMPD on April 23.Deputy Chief Ian Cyr and Chief Tyrone Parham provided opening and welcom
Two phases of Massena Central School capital project underway simultaneously nny360.com - get the latest breaking news, showbiz & celebrity photos, sport news & rumours, viral videos and top stories from nny360.com Daily Mail and Mail on Sunday newspapers.
MASSENA â Now that school doors are closed for the summer, contractors are working simultaneously on two phases of the Massena Central School Districtâs $49.6 million capital project.
âWe have a lot of construction under way,â said Edward Bernhauer, an architect for the IBI Group, the districtâs architectural firm.
He said work being done was the second summer of phase one, a carryover from 2020, and the initiation of phase two. Phase one work is primarily site work, as well as roofing work and roofing replacement.
âWhat that basically does is makes all of our facilities and all of our buildings active with work currently going on,â Mr. Bernhauer said.
MASSENA â Contracts have been awarded for phase two of the Massena Central School Districtâs $49.6 million capital project, with work starting this summer.
The general construction contract was awarded to Bette & Cring, LLC with a base bid of $4,665,000. The mechanical construction contract was awarded to Northern Mechanicals, Inc. with a base bid of $7,715,000. The electrical construction contract was awarded to S&L Electric, Inc. with a base bid of $2,569,000.
The low bidder for the electrical work had been Watson Electric, Inc., but they withdrew their bid because of a mathematical error, and the contract was awarded to the next lowest bidder.
MASSENA — Contracts have been awarded for phase two of the Massena Central School District’s $49.6 million capital project, with work starting this summer.