Ohio Supreme Court stops collection of nuclear plant subsidy Follow Us
Question of the Day By MARK GILLISPIE - Associated Press - Monday, December 28, 2020
CLEVELAND (AP) - The Ohio Supreme Court on Monday issued a temporary stay to stop collection of a fee from nearly every electric customer in the state starting Jan. 1 to subsidize two nuclear power plants, a provision included in a scandal-tainted bill approved by the state Legislature in July 2019.
The order signed by Chief Justice Maureen O’Connor comes a week after a judge in Franklin County issued a preliminary injunction to stop collection of the fees.
Ohio Supreme Court orders temporary stop to nuclear bailout fees from House Bill 6 Mark Gillispie, Associated Press
Replay Video UP NEXT
The Ohio Supreme Court on Monday issued a temporary stay to stop collection of a fee from nearly every electric customer in the state starting Jan. 1 to subsidize two nuclear power plants, a provision included in a scandal-tainted bill approved by the state Legislature in July 2019.
Common Pleas Judge Chris Brown in his ruling from the bench last Monday said, “To not impose an injunction would be to allow certain parties to prevail. It would give the OK that bribery is allowed in the state of Ohio and that any ill-gotten gains can be received.
The Ohio Supreme Court on Monday issued a temporary stay to stop collection of a fee from nearly every electric customer in the state starting Jan. 1 to subsidize two nuclear power plants, a provision included in a scandal-tainted bill approved by the state Legislature in July 2019.
Common Pleas Judge Chris Brown in his ruling from the bench last Monday said, “To not impose an injunction would be to allow certain parties to prevail. It would give the OK that bribery is allowed in the state of Ohio and that any ill-gotten gains can be received.
The Ohio Manufacturers’ Association appealed to the Supreme Court earlier this month after the Public Utilities Commission of Ohio in August cited the legislation known as HB6 in issuing an order approving collection of the fees and then refused to reconsider the group’s request for a new hearing.
The Associated Press
CLEVELAND The Ohio Supreme Court on Monday issued a temporary stay to stop collection of a fee from nearly every electric customer in the state starting Jan. 1 to subsidize two nuclear power plants, a provision included in a scandal-tainted bill approved by the state Legislature in July 2019.
The order signed by Chief Justice Maureen O’Connor comes a week after a judge in Franklin County issued a preliminary injunction to stop collection of the fees.