The Sheridan County Commission has voted to reject the bids they received on the Wolf Creek Road project.
County Engineer Ken Muller explained that the project is a cooperative effort with the Town of Ranchester for a portion of Wolf Creek Road within their town limits.
Muller said the roa
Sheridan County's Commissioners have approved the appointment of County Engineer Ken Muller as the viewer in the vacation of portions of two properties within the county.
Muller will act as the viewer on the vacation of a portion of Carbon Hill Road and the vacation of Story Avenue between Blocks
A vacation of public rights-of-way in he Downers Addition in Sheridan County has been approved and accepted by the county commission.
The commission appointed County Engineer Ken Muller to act as the viewer in the matter, and he discussed the proposal with them during their last meeting.
T
An amendment to the agreement between the Sheridan County and Morrison-Maierle, Inc. to add to the cost for professional services on the Brooks Street Greenspace Project has been approved by the county commission.
County Engineer Ken Muller explained why there was an increase in costs and therefo
The final plat for the Powder Horn Estates, Phase 1 Subdivision has been approved by the Sheridan County Commission.
The application from Powder Horn Ranch–2, LLC was brought before the commission during their recent meeting and was explained by County Planner Mark Reid.
Commissioner Nick