Court order to remove the 150-MW Texas project could be yellow flag to other companies building on Native American sites without full rights above ground and below according to attorneys.
Court order to remove the 150-MW Texas project could be yellow flag to other companies building on Native American sites without full rights above ground and below according to attorneys.
Court order to take down 150-MW Oklahoma project could be yellow flag to other companies building on Native American sites without full rights above ground and below according to two outside attorneys.
The district secured $17 million in bonds based on the expected wind farm revenue, $500,000 annually, for desperately needed new high school and middle school facilities.