Examiner News Briefs, March 3
Township Committee members in Upper Freehold Township have authorized decreases in three contracts for improvements to local roads that will result in final payments of $829,533, $787,215 and $769,445.
On Feb. 4, committee members authorized the decreases with Asphalt Paving Systems for road improvement projects that began in 2019.
The original contracts were in the amount of $1 million for Jonathan Holmes Road, $967,800 also for Jonathan Holmes Road, and $911,200 for Millers Mill Road.
The $1 million contract for Jonathan Holmes Road was reduced by $237,596 to reach a final total of $829,533.
The $967,800 contract for Jonathan Holmes Road was reduced by $180,584 to reach a final total of $787,215.