Prior to the chimney s demolition, the two-meter-long repair shop at Tata Steel s Jamshedpur plant was demolished as a rehearsal. 28.11.2022, Sputnik International
As per the demolition plans by the two firms, fire tenders, water sprinklers, and other personnel will be deployed in order to keep the dust at bay. Besides, the two firms are also planning to install a cloth net on each floor of the two buildings to avoid debris from occupying a large space. Noida Twin Tower Demolition: Razing of Supertech Towers Might Create 300 Metres of Dust Cloud; Here s How Authorities Plan To Tackle.
Asked if he is nervous, Mehta told IANS: "No, not at all. We are confident." He then detailed how the two towers, nestled between upmarket societies ATS Village and Emerald Court in Sector 93A, will be brought down. "We will start with Ceyane in B1 and the top of Apex towards Aster 2 and Aster 3," said Mehta. 📰 Noida Twin Tower Demolition: Supertech Tower Project Manager Mayur Mehta Breaks Down Plan to Raze Towers on August 28.