Another four months of road closures and temporary removal of carparks, this time along
Queenstown’s Camp Street and Earl St, will start next week but the end is far from sight.
Queenstown council contractors will start digging trenches and installing 600 metres of
wastewater pipe along Camp St next week as the Rec Ground pump station and wastewater upgrade which started 12 months ago moves to the next phase.
Council property and infrastructure boss Peter Hansby says the disruption there will continue till late September contractors will be talking with directly-affected businesses about managing disruptions and maintaining access as the project moves along Camp St.