Harvey County outlines road repairs for spring, summer
The Kansan
Spring means one thing for drivers construction season has arrived. The Harvey County Road and Bridge department will begin its 2021 asphalt patching program this week.
The work will begin in the City of Sedgwick on Commercial Avenue from First to Eighth streets, followed by Washington Avenue from First to Eighth. Patching on these streets is estimated to take two weeks, contingent on weather.
After that is completed, the patching schedule will next continue to Ridge Road from US-50 highway to the Harvey/McPherson county line.
Other locations included in the 2021 patching schedule include: