Vexus Contracting LLC won the bid for the Expo building storage project just north of the covered arena.
Claremore City Engineer Garrett Ball said this project costs $327,000 and includes footings, a concrete slab and the 100-foot by 125-foot metal building package.
Ball said this project will be primarily used to store portable bleachers and miscellaneous items.
âThe hope is to clean the whole site up a bit,â he said.
Ball said the project will start in 30â45 days and Vexus Contracting LLC will have 120 days to complete it.
âIn conjunction with this project, weâve also done some substantial storm drain improvements there at the expo,â he said. âWere hoping this project as a whole ends up improving the storm water discharge from the site.