GAO: Design Delays on Columbia Sub Program Leading to Construction Delays, Cost Increases
Artist’s rendering of the Columbia-class SSBN submarine. US Navy Image
The Government Accountability Office released a new report that warns Columbia-class ballistic-missile submarine cost and schedule plans are at risk due to problems with a new digital design tool and cascading effects stemming from the design challenges.
The report – Columbia Class Submarine: Delivery Hinges on Timely and Quality Materials from an Atrophied Supplier Base – explains that Columbia program prime contractor “Electric Boat faces persistent problems with its design tool leading to cost increases and schedule delays during the design phase. Late completion of design products threatens to impede construction progress and indicates challenges in the Columbia class program’s abil
POLITICO
Get the Morning Defense newsletter
Email
Sign Up
By signing up you agree to receive email newsletters or updates from POLITICO and you agree to our privacy policy and terms of service. You can unsubscribe at any time and you can contact us here. This sign-up form is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
Presented by
PROGRAMMING NOTE: Morning Defense will not publish on Monday, Jan. 18. We ll be back on our normal schedule on Tuesday, Jan. 19. Please continue to follow Pro Defense.
Editor’s Note: Morning Defense is a free version of POLITICO Pro Defense s morning newsletter, which is delivered to our subscribers each morning at 6 a.m. The POLITICO Pro platform combines the news you need with tools you can use to take action on the day’s biggest stories. Act on the news with POLITICO Pro.