Place North West | Delays hit High Street s £50m Cheshire Junction

Sarah Townsend Completion of the residential development in central Warrington has been pushed back several months to early next year as construction work pauses while the developer reviews its delivery programme. Newcastle-based High Street Group is building the £48.7m Cheshire Junction, an eight-storey block planned to deliver 362 apartments on a former industrial site on John Street. The scheme also includes a car park with 796 spaces. As of last November, main contractor Nobles Construction had completed the external frame and begun work erecting the external walls and creating the internal structure of the apartments, with fit-out to follow, according to a project update sent to investors at the time. The scheme was intended to complete by November 2021.