The Harington Street transport hub under construction in Tauranga.
Photo: Supplied
The council pulled the plug on the defective and partly built Harington St carpark in June last year, due to seismic concerns.
He outlined his concerns about the council s process during the project - these included going for the cheapest option, a lack of a business case or overall plan for procurement, unclear responsibilities and unclear purpose of the project.
The council had spent $19m on the project when it decided to halt construction.
It was estimated it would cost $9.8m to demolish the building and restore the site.