By cassie mcclure for lcu
• Apr 1, 2021 During the 2019 New Mexico Legislative Session, a $1,006,370.00 grant was approved for the Las Cruces Septic Systems Replacement project, Hacienda Acres is one of two areas in Las Cruces that will benefit from the grant funding. Approved by the Las Cruces Utilities (LCU) Board of Commissioners via Resolution No. 20-21-LCU026, the Hacienda Acres Phase II Sewer Improvements Project will now go to construction.
The Hacienda Acres Phase II Sewer Improvements project consists of installing an 8-inch gravity sewer main, utility holes, and a 4-inch PVC sewer service line in Calle de Ranchero and Avenida del Sol Road. Installation of the new sewer main and services will allow for 32 sewer connections for residents along these streets as a part of this septic replacement project.