Yelahanka-Penukonda track doubling delayed
.
The work is now set to finish in October due to acquisition issues in Andhra Pradesh, say railway officials
The work to double the railway tracks between
Yelahanka and
Penukonda is likely to be completed by October. Once this important track is doubled it will help the railways to increase the speed of the trains and to avoid frequent halts due to trains crossing.
Sources from the
South Western Railways (SWR) said that out of the 120.55-kilometre-long stretch, additional tracks for another 48 kilometres are yet to be laid. Although the project received approval in 2015, it faced some hurdles while acquiring land in Andhra Pradesh. This delayed the project.
BirurKarnatakaIndiaTumakuruChikjajurYelahankaBengaluruPenukondaAndhra-pradeshDharmavaramChikballapurJolarpettaiAdditional weekly special train between Mumbai and Mysuru. https://t.co/XU1mmd0cp6 Central Railway (@Central Railway) 1612834819000
The train will have the load combination of 17 coaches one coach of AC (one tier), three AC coaches (three tier), eight sleeper class and five second class seating.
The special train will have stoppages at Kalyan, Karjat (for 01035 only), Pune, Satara, Karad, Sangli, Miraj, Kudachi, Ghatprabha, Belagavi, Londa, Alnavar, Dharwar, Hubballi, Haveri, Ranibennur, Harihar, Davangere, Birur, Kadur, Arsikere, Hassan, Hole Narsipur and Krishnarajanagar.
Read Also
BirurKarnatakaIndiaDharwarUttar-pradeshAlnavarSataraMaharashtraPuneRanibennurDadarBelagavi