By the time of the supervising engineer's assessment, which took place on May 12th, the deadlines for completing the Počitelj bridge construction had been egregiously exceeded by 218 days. The selected companies, Sinohydro Corporation Limited and Powerchina Roadbridge Group, subcontracted the span structure construction of the Počitelj bridge to a third company (from BiH). China Gezhouba Group Co. LTD provided falsified documentation
FBiH Motorways: Počitelj Bridge has not been compromised in any way avaz.ba - get the latest breaking news, showbiz & celebrity photos, sport news & rumours, viral videos and top stories from avaz.ba Daily Mail and Mail on Sunday newspapers.
Fokus.ba is in possession of the OLAF document in which Voloder is accused of having ordered the Commission to exclude the bidder with the lowest bid for a section of Tunel Buna - Kvanj. OLAF's investigations in Croatia led to the arrest of high-ranking officials