Veligonda Project Tunnel-1 Works Completed In Record Time
Jan 14, 2021, 16:10 IST
PRAKASAM: The Tunnel-1 works of the Veligonda project, which aims to irrigate the dry lands in Prakasam, Nellore and Kadapa districts, were done at a record pace and completed by Wednesday.
The Andhra Pradesh government has taken all efforts to ensure the completion of these long-pending works as per the promise made by the Chief Minister YS Jagan Mohan Reddy and the Krishna waters will be diverted in the coming season. Accordingly, the Tunnel-1 project works were expedited and completed by yesterday.
With a total length of 3.6 km, the tunnel was dug at an average of 9.23 m per day.

Related Keywords

Srisailam ,Andhra Pradesh ,India ,Prakasam ,Jalandhar ,Punjab ,Kadapa ,Nellore ,Nallamala Sagar ,Jagan Mohan Reddy ,C Narayana Reddy ,J Shyamala Rao ,Kumar Yadav ,Megha Engineering Infrastructures Ltd ,Water Resources Department ,Chief Minister ,Mohan Reddy ,Saved On Veligonda Project Through Reverse ,Ministerp Anil Kumar Yadav ,Megha Engineering ,Water Resources Secretaryj Shyamala Rao ,Narayana Reddy ,Tunnel 1 Veligonda Project Completed ,Veligonda Project ,Ys Jagan Mohan Reddy ,Tunnel 1 Works Record Time ,How Longis Tunnel 1 Of Veligonda Projectsm Meil Project Contractors ,Veligonda ,Tunnel 1 ,Srisailam Reservoir ,Nallamalla Sagar ,ஸ்ரிசைலாம் ,ஆந்திரா பிரதேஷ் ,இந்தியா ,பிரகாசம் ,ஜலந்தர் ,பஞ்சாப் ,கடபா ,நெல்லூர் ,ஜெகன் மோகன் சிவப்பு ,ஜு ஷியாமள ராவ் ,குமார் யாதவ் ,மேகா பொறியியல் உள்கட்டமைப்புகள் லிமிடெட் ,தண்ணீர் வளங்கள் துறை ,தலைமை அமைச்சர் ,மோகன் சிவப்பு ,மேகா பொறியியல் ,நாராயணா சிவப்பு ,ய்ஸ் ஜெகன் மோகன் சிவப்பு ,சுரங்கம் வேலை செய்கிறது பதிவு நேரம் ,சுரங்கம் ,ஸ்ரிசைலாம் நீர்த்தேக்கம் ,

© 2024 Vimarsana

comparemela.com © 2020. All Rights Reserved.