The building has been officially handed over to Cardiff and Vale University Health Board (CAVUHB).
As of Monday, February 8, building work on the new surge facility has been completed, just 20 weeks after construction first started.
This means that the ownership of the modular build has been given to the Health Board from the primary contactors, Darwin Group Ltd.
Delivering an additional 234 beds, the completion of the Southern Wing of the site by Darwin Group brings the total capacity of the modular building to 400 patients; this, with the additional 200 beds available across the Health Board’s sites, will allow CAVUHB to provide 600 beds in total which meets the capacity requirement as predicted by Welsh Government and local intelligence data and modelling in the event of another COVID-19 spike.