Wind turbines – majestic, metallic, monolithic giants – stand in intermittent long lines across the bare, winter windswept Wyoming landscape just a few miles outside of Douglas.
There’s a lot of them – 192, to be exact – changing the usual landscape visuals folks are used to seeing between WYO59 and WYO93.
WYO59 cuts through the middle of the 499-foot tall towers, their blades slowly, methodically rotating as they create 533 megawatts of wind generated electricity.
NextEra Energy Resources’ $650 million Cedar Springs Windfarm, phases I, II and III – are online and fully operational as of Dec. 11, according to NextEra’s Project Manager Ryan Fitzpatrick.
The company broke ground on the project in October 2019, and had cited Dec. 31 as their completion date.

Related Keywords

Wyoming ,United States ,Ryan Fitzpatrick ,Nextera Energy Resource ,Nextera Energy Resources ,Pacificorp ,Era Energy Resource ,Cedar Springs Windfarm ,Project Manager Ryan ,Aviation Detection Lighting System ,Cedar Springs ,Era Energy Resources ,Converse County ,வயோமிங் ,ஒன்றுபட்டது மாநிலங்களில் ,ரியான் ஃபிட்ஸ்‌ப்யாட்ரிக் ,னெக்ஷ்டேர ஆற்றல் வள ,னெக்ஷ்டேர ஆற்றல் வளங்கள் ,சகாப்தம் ஆற்றல் வள ,ப்ராஜெக்ட் மேலாளர் ரியான் ,விமான போக்குவரத்து கண்டறிதல் விளக்குகள் அமைப்பு ,சிடார் நீரூற்றுகள் ,சகாப்தம் ஆற்றல் வளங்கள் ,உரையாடல் கவுண்டி ,