Whatever method builders of the Mountain Valley Pipeline use to get from one side of a waterbody to another — either a trench dug along the bottom or a tunnel bored below — it won’t be happening anytime soon.
The latest delay came Monday, when the U.S. Army Corps of Engineers said it will extend to Dec. 31 a deadline for state regulators to decide if digging trenches will pose an unacceptable risk to the streams and wetlands of Southwest Virginia.
Earlier this year, the Virginia Department of Environmental Quality sought a postponement from July 2, which it said would not allow enough time for a water quality certification that requires detailed analysis and public comment.

Related Keywords

Mountain Valley ,Virginia ,United States ,New River ,West Virginia ,Natalie Cox ,Peter Anderson ,Roberta Bondurant ,David Sligh ,Melanie Davenport ,Todd Normane ,Army Corp ,Energy Regulatory Commission ,Virginia Department Of Environmental Quality ,Us Army Corps Of Engineers ,Mountain Valley Pipeline ,Virginia Department ,Environmental Quality ,Federal Energy Regulatory ,Protect Our Water ,Southwest Virginia ,Clean Water Act ,Wild Virginia ,மலை பள்ளத்தாக்கு ,வர்ஜீனியா ,ஒன்றுபட்டது மாநிலங்களில் ,புதியது நதி ,மேற்கு வர்ஜீனியா ,நடாலி காக்ஸ் ,பீட்டர் ஆண்டர்சன் ,ரோபர்ட்டா பிணைப்பு ,டேவிட் பனியில் சறுக்கி ஓடும் வாகனம் ,மெலனி டேவன்ஸ்போர்ட் ,இராணுவம் கார்ப் ,ஆற்றல் ஒழுங்குமுறை தரகு ,வர்ஜீனியா துறை ஆஃப் சுற்றுச்சூழல் தரம் ,எங்களுக்கு இராணுவம் கார்ப்ஸ் ஆஃப் பொறியாளர்கள் ,மலை பள்ளத்தாக்கு குழாய் ,வர்ஜீனியா துறை ,சுற்றுச்சூழல் தரம் ,கூட்டாட்சியின் ஆற்றல் ஒழுங்குமுறை ,ப்ரொடெக்ட் அவர் தண்ணீர் ,தென்மேற்கு வர்ஜீனியா ,சுத்தமான தண்ணீர் நாடகம் ,காட்டு வர்ஜீனியா ,

© 2025 Vimarsana

comparemela.com © 2020. All Rights Reserved.