Principal Secretary said that the project is of national significance and all the bottlenecks and hurdles need to be removed with inter agency coordination ensuring project completion within stipulated time. ‘Timely completion of the prestigious railway project by 2022 is our only priority’, he maintained.
It is pertinent to mention that the works from Reasi to Banihal are being executed by Konkan Railways Corporation Limited, while the rest are being taken care of by IRCON Limited.
Principal Secretary asked the executing agencies and the Power Development Department for resolution of the most pressing issues including payment to contractors. He also set deadlines for completion of the project which were amicably accepted by all stakeholders present at the meeting.

Related Keywords

Jammu ,Jammu And Kashmir ,India ,Konkan ,Maharashtra ,Udhampur ,Baramulla ,Rohit Kansal ,Mir Bazar Qazigund ,Power Development Department ,Konkan Railways Corporation ,Principal Secretary ,Udhampur Srinagar Baramulla Rail Link ,Budgam Grid Sub Station Railway ,Konkan Railways Corporation Limited ,Managing Director ,Chief Engineers ,Director Finance ,Secretary Technical ,Deputy Director Planning ,Chief Engineer ,ஜம்மு ,ஜம்மு மற்றும் காஷ்மீர் ,இந்தியா ,கொங்கன் ,மகாராஷ்டிரா ,உதம்பூர் ,பாரமுல்லா ,ரோஹித் கன்சால் ,பவர் வளர்ச்சி துறை ,கொங்கன் ரயில்வே நிறுவனம் ,ப்ரிந்ஸிபல் செயலாளர் ,உதம்பூர் ஸ்ரீநகர் பாரமுல்லா ரயில் இணைப்பு ,பௌகம் கட்டம் துணை நிலையம் ரயில்வே ,கொங்கன் ரயில்வே நிறுவனம் வரையறுக்கப்பட்டவை ,நிர்வகித்தல் இயக்குனர் ,தலைமை பொறியாளர்கள் ,இயக்குனர் நிதி ,செயலாளர் தொழில்நுட்ப ,துணை இயக்குனர் திட்டமிடல் ,தலைமை பொறியாளர் ,

© 2025 Vimarsana

comparemela.com © 2020. All Rights Reserved.