Equinor : Revised start-up date for Hammerfest LNG
édité le 26/04/2021 - Plus de news de "Equinor" - Voir la fiche entreprise de "Equinor"
Based on extensive analyses and mapping of damages, Equinor has updated the schedule for repair and start-up of the LNG plant on Melkøya after the fire on 28 September 2020. Due to the comprehensive scope of work and Covid-19 restrictions, the revised estimated start-up date is set to 31 March 2022.
Even though the fire in September 2020 was limited to the air intake of one of the plant’s five big gas turbines, the fire and firefighting caused substantial damage to the plant.

Related Keywords

,Greteb Haaland ,Europetrole ,News ,Mploi ,Market Place ,Nnuaire ,Ntreprises ,Etrole ,Petrol ,Ydrocarbure ,A ,Az ,Az Naturel ,Rut ,Brent ,Essence ,Uper ,Uper Sans Plomb ,As Oil ,Uile ,Ubrifiant ,Fuel ,Arburant ,Itume ,Raisse ,Utane ,Pl ,Affinage ,Pipeline ,Azoduc ,Ortail ,Late Forme ,Onsommation ,Ipp ,Ours Du Brut ,Tation Service ,Soil ,Oil And Gas ,Gasoline ,Petroleum Industry ,Energy ,Nshore ,Ffshore ,Engineering ,Il Well ,எவ்ஸ் ,அஸ் ,ரூட் ,வாடகை ,ப்ல் ,இப்ப் ,நான் L ,

© 2025 Vimarsana

comparemela.com © 2020. All Rights Reserved.