The Bulk Power Supply Point (BPS) being constructed at Pokuase in the Greater Accra Region is 95 per cent complete and on schedule for handover to the government at the end of July 2021.
According to the site engineers, all other ancillary facilities to support its full function have also been completed.
The Technical Controller of the Millennium Development Authority (MiDA), Mr William Amuna, gave the assurance when he led a team working on the project, to conduct the Minister of Energy, Dr Matthew Opoku Prempeh around the project Tuesday (April 20, 2021).
He said but for the outbreak of the coronavirus disease (COVID-19) outbreak in Ghana which forced the suspension of work for a while and supply of materials from China, the project would have been completed earlier.