Over-schedule and rising costs: Tauranga's BayLink flyovers delayed another year
21 Jan, 2021 04:00 PM
6 minutes to read
The cost of one of the Bay of Plenty's largest roading projects has jumped to $262 million and it will be delayed by another year.
The Baypark to Bayfair Project, also known as Baylink or
B2B, on State Highway 2 at Mount Maunganui will see flyovers built bypassing two busy roundabouts.
When the first sod was turned on this phase of the project in 2017, it was expected to cost $120m and be finished by 2020. The most recent estimate pegged the cost at $146m and the completion date in 2022.

Related Keywords

Bay Of Plenty ,New Zealand ,Waikato ,Auckland ,Mount Maunganui ,New Zealand General ,Brendan Bisley ,Lyall Thurston ,Jo Wilton ,John Mccarthy ,Bay Of Plenty Regional Transport Committee ,Zealand Transport Agency Waka Kotahi ,Bayfair Shopping Centre ,University Of Auckland ,Tauranga City Council ,Bayfair Project ,State Highway ,New Zealand Transport Agency Waka Kotahi ,Plenty Jo Wilton ,Southern Motorway ,Bayfair Shopping ,City Council ,Plenty Regional Transport Committee ,Western Bay ,Plenty Times ,வளைகுடா ஆஃப் ப்லெஂடீ ,புதியது ஜீலாந்து ,வைகாடோ ,ஆக்லாந்து ,புதியது ஜீலாந்து ஜநரல் ,லையல் தர்ஸ்டன் ,ஜோ வில்டன் ,ஜான் ம்க்கார்தீ ,வளைகுடா ஆஃப் ப்லெஂடீ பிராந்திய போக்குவரத்து குழு ,வளைகுடா கடையில் பொருட்கள் வாங்குதல் மையம் ,பல்கலைக்கழகம் ஆஃப் ஆக்லாந்து ,வளைகுடா ப்ராஜெக்ட் ,நிலை நெடுஞ்சாலை ,ப்லெஂடீ ஜோ வில்டன் ,தெற்கு மோட்டார் பாதை ,வளைகுடா கடையில் பொருட்கள் வாங்குதல் ,நகரம் சபை ,ப்லெஂடீ பிராந்திய போக்குவரத்து குழு ,மேற்கு வளைகுடா ,ப்லெஂடீ முறை ,

© 2024 Vimarsana

comparemela.com © 2020. All Rights Reserved.