"The first one I wanted to mention was the FirstBank Southwest Tower," Andrew
Freeman, the city's managing director of Planning and Development Services said with regard to the residential unit project. "That was permitted on Oct. 7 and is currently under construction. Both floors have been framed out. The HVAC vendor is currently working on the mechanical. They anticipate being completed with mechanical and start sheet rocking the 11th floor by mid-January. Then they'll start mechanical on the 10th floor once that's wrapped up. They believe the 10th floor will take six to eight weeks to complete the mechanical before they start sheet rocking that phase."