Oceanside dredging project in full swing
May 6, 2021,
by
Eldin Ganic
The City of Oceanside Harbor, CA, has just released the latest update on their dredging project, conducted by Manson Construction.
So far, the contractor dredged 215,000 cubic yards of sand that was placed on City beaches.
The current outfall pipe is located just north of Surfrider Way.
Due to recent Grunion runs on the beach, all remaining dredged sand will be deposited at that location.
USACE has approved a total of 305,000 cubic yards to be removed from the Harbor inlet. An additional 90,000 cubic yards will be dredged before Manson begins demobilization.