The review found that the lead ship of the Columbia-class submarines is delayed 12-16 months, blocks four and five of Virginia-class submarines are delayed 24-36 months and the third Ford-class aircraft carrier is delayed 18-26 months — all of which Newport News Shipbuilding plays a role in constructing.