Napier outfall repair complete - replacement challenges loom
4 Feb, 2021 11:03 PM
3 minutes to read
A boat works on the Napier city wastewater outfall off the Awatoto coast. Photo / Paul Taylor
A boat works on the Napier city wastewater outfall off the Awatoto coast. Photo / Paul Taylor
Hawkes Bay Today
Contractors employed by the Napier City Council have completed repairs to the leaking underwater Awatoto wastewater outfall pipe in a four-month project which originally was planned for just one month.
The weather-dependant project, for which the council set a budget of $500,000, began in September, with hopes it would be complete by the end of October.

Related Keywords

Hawke Bay ,New Zealand General ,New Zealand ,Whakatu ,Napier City ,Awatoto , ,Napier City Council ,Salvage Ltd ,Hawke Bay Regional Council ,Council Sustainable Napier ,Sustainable Napier ,New Zealand Diving ,Warner Engineering ,Bay Regional Council ,Long Term Plan ,Bay Today ,Wastewater Treatment ,Outfall Masterplan ,Napier ,Outfall ,Repair ,Complete ,Replacement ,Challenges ,Bloom ,Contractors ,Unemployed ,City ,Council ,Have ,Completed ,Repairs ,Leaking ,Underwater ,Waste Water ,Pipe ,Four Month ,Project ,Which ,Originally ,Planned ,Ijust ,Month ,பருந்து வளைகுடா ,புதியது ஜீலாந்து ஜநரல் ,புதியது ஜீலாந்து ,நேப்பியர் நகரம் ,நேப்பியர் நகரம் சபை ,காப்பு லிமிடெட் ,பருந்து வளைகுடா பிராந்திய சபை ,சபை நிலையான நேப்பியர் ,நிலையான நேப்பியர் ,புதியது ஜீலாந்து டைவிங் ,எச்சரிக்கை பொறியியல் ,வளைகுடா பிராந்திய சபை ,நீண்டது கால திட்டம் ,வளைகுடா இன்று ,கழிவு நீர் சிகிச்சை ,நேப்பியர் ,பழுது ,முழுமை ,மாற்று ,சவால்கள் ,தறி ,ஒப்பந்தக்காரர்கள் ,வேலை ,நகரம் ,சபை ,வேண்டும் ,நிறைவு ,கசிவு ,நீருக்கடியில் ,கழிவு தண்ணீர் ,குழாய் ,நான்கு மாதம் ,ப்ராஜெக்ட் ,எந்த ,ஒரிஜிநலீ ,திட்டமிடப்பட்டுள்ளது ,வெறும் ,மாதம் ,

© 2025 Vimarsana

comparemela.com © 2020. All Rights Reserved.