Controversy-riddled Malawi Rural Electrification Programme Phase 9 (Marep 9) is set to miss its March 31 2024 deadline with just 20 sites out of 469 having power infrastructure constructed. Speaking in an interview yesterday, Ministry of Energy Principal Secretary Alfonso Chikuni said the March 31 deadline was not practical as construction of the power lines

Related Keywords

Malawi ,Mathews Ngwale ,Alfonso Chikuni ,Ministry Of Energy ,Department Of Energy ,Electricity Supply Corporation Of Malawi ,Malawi Revenue Authority ,Parliamentary Committee On Health ,Malawi Rural Electrification Programme ,Tonse Alliance ,Corruption Bureau ,Ministry Of Energy Principal ,Parliamentary Committee On Natural Resources ,Energy Principal Secretary Alfonso Chikuni ,Malawi Revenue ,Parliamentary Committee ,Natural Resources ,Climate Change ,Anti Corruption Bureau ,Electricity Supply Corporation ,Front Page ,National News ,