Manatee County scheduled road projects
44th Avenue East
Projected cost: $101,304,276
Estimated completion: Dec. 2029
Moccasin Wallow Road
What: Three-segment plan to widen from two lanes to four or six, depending on the segment, from U.S. Route 301 to U.S. Route 41
Projected cost: $42,226,247
Estimated completion: Dec. 2025
What: Reconstruction of Verna Bethany Road to align with Verna Road at State Road 70
Projected cost: $2,519,682
Estimated completion: Dec. 2023
Manatee County commissioners have stated their desire to make road construction a top priority in the next year.
However, they said deciding which projects come first and how to pay for those projects is more difficult.