Major milestone for the Esquimalt Harbour project
December 22, 2020,
by
Zlatan Hrvacevic
After months of hard work, the $162.5 million-Esquimalt Harbour Remediation Project has reached a major milestone with the completion of remediation at the Y-Jetty & Lang Cove site, reports Fraser River Pile and Dredge (FRPD).
Beginning in January 2019, the Y-Jetty & Lang Cove Remediation Project focused on addressing contamination that had accumulated in the harbour seabed after almost 200 years of commercial, military and industrial use.
According to FRPD, during the remediation of the Y-Jetty & Lang Cove site, over 48,500 cubic metres of sediment was dredged from the seabed. The sediment that was removed contained an estimated 14,341 tonnes of contaminants (including aluminum, copper, iron, lead and mercury).

Related Keywords

Esquimalt ,British Columbia ,Canada ,Esquimalt Harbour ,Fraser River ,Newfoundland ,Canadian ,Lang Cove ,Department Of Fisheries ,Safety Environment ,Esquimalt Harbour Remediation Project ,Fraser River Pile ,Lang Cove Remediation Project ,Parliamentary Secretary ,Canadian Coast Guard ,Esquimalt First Nations ,Milestone Environmental ,Base Safety ,எஸ்‌க்விமல்‌ட் ,பிரிட்டிஷ் கொலம்பியா ,கனடா ,எஸ்‌க்விமல்‌ட் துறைமுகம் ,ஃப்ரேசர் நதி ,நியூஃபவுண்ட்லேண்ட் ,கனடியன் ,லாங் கோவ் ,துறை ஆஃப் மீன்வளம் ,பாதுகாப்பு சூழல் ,எஸ்‌க்விமல்‌ட் துறைமுகம் பரிகாரம் ப்ராஜெக்ட் ,ஃப்ரேசர் நதி குவியல் ,லாங் கோவ் பரிகாரம் ப்ராஜெக்ட் ,பாராளுமன்றம் செயலாளர் ,கனடியன் கடற்கரை காவலர் ,எஸ்‌க்விமல்‌ட் முதல் நாடுகள் ,மைல்கல் சுற்றுச்சூழல் ,அடித்தளம் பாதுகாப்பு ,

© 2025 Vimarsana

comparemela.com © 2020. All Rights Reserved.