Current Progress
Maine East: Field House finishes continue toward completion. 2nd Floor Fitness Room flooring is ongoing as is casework and finishes in locker rooms. Elevator installation is wrapping up as is HVAC systems as we move toward completion. Progress continues to maintain schedule.
Sitework around the addition scheduled to commence over the next few weeks weather dependent.
The Center Court (Area E) demolition is wrapping up. Mechanical, electrical, plumbing and fire protection installation is ramping up. Steel install for the new skylight opening is starting. Additionally, the demolition of the connecting link has started. Progress continues inline with our schedule.