KWA speeds up work on sewerage scheme
Updated:
Updated:
Hurdles to Jagathy-Kootanvila scheme, commissioned in 1996, include land acquisition
Share Article
Hurdles to Jagathy-Kootanvila scheme, commissioned in 1996, include land acquisition
The Kerala Water Authority (KWA) has speeded up work on the long-delayed Jagathy-Kootanvila sewerage scheme, but indications are that the capital city may have to wait a bit longer to see this project commissioned as the KWA faces a number of hurdles.
Although the KWA launched the Jagathy-Kootanvila scheme in 1996, the commissioning has been delayed due to problems in acquiring land and the financial constraints of the KWA.
The KWA is now taking steps to quicken the pace of work and commission the scheme. Pending works include drawing the pipeline across the Killiyar. Land acquisition is required on both banks of the river for laying the pipes. Once this work is completed, the scheme can be partially commissioned, KWA officials said.