comparemela.com


FERC's decision in
Broadview Solar, LLC (discussed here) couldn't even make it to its first birthday before FERC said "never mind," that such decision was a mistake. Reversing the reasoning of its earlier order, FERC held in its order addressing arguments on rehearing that a 160 MW solar facility with a 50 MW battery could qualify as a small power production qualifying facility (SPP QF), so long as the facility's "net output to the electric utility (i.e., at the point of interconnection), taking into account all components necessary to produce electric energy in a form useful to an interconnected entity," was 80 MW or less. The Commission's rationale largely mirrored the arguments put forth in dissent to the original order by then-Commissioner, now-Chairman, Glick. But the rehearing order still did not address important considerations in evaluating compliance with PURPA's 80 MW limit, and (like the original order) drew a dissent. It is doubtful that the new order will be the last we hear on this issue, although any load serving entity challenging the new order (or the policy, if and when applied to them in an analogous order), will need an appellate panel of strict statutory constructionists.

Related Keywords

,Steptoe Johnson ,Chevron ,Broadview Solar ,A Court ,Commissioner Glick ,Shaun Boedicker ,Jenniferl Key ,ஸ்டெப்டோ ஜான்சன் ,செவ்ரான் ,அகலக்காட்சி சூரிய ,ஆணையர் க்ளிக் ,

© 2024 Vimarsana

comparemela.com © 2020. All Rights Reserved.