comparemela.com


Four bids have been received in answer to the request for proposals – three are for bored tunnels and the other is for an immersed structure.
Azzopardi said this alternative, submitted by the only Maltese consortium, had not been rejected because IM had been advised that restricting the proposals to bored tunnels might give rise to appeals that would delay the tendering process.
He explained that IM’s conceptual design was for a 14-kilometre horseshoe-shaped tunnel running underground and under the seabed between l-Imbordin, in St Paul’s Bay, and a road near Kenuna Tower, in Nadur.
But this was not the final design or technology – whether bored or immersed. That would only be determined once bidders who satisfied the criteria passed the first phase of the evaluation process and moved to the second phase.

Related Keywords

Gozo ,Malta General ,Malta ,Kenuna Tower ,Nadur ,Comino ,Qala ,Maltese ,Maria Grazia Cassar ,Fredrick Azzopardi ,Robert Schembri ,Mizzi Organisation ,Malta Gozo Fixed Link ,Malta Gozo Consortium ,Equitix Itochu Yapi Consortium ,Infrastructure Malta ,Salini Impregilo Spa ,Gozo Consortium ,Gozo Fixed Link Limited ,Alberta Fire ,Grazia Cassar ,Gozo Channel ,Contracts Department ,கோஸோ ,மால்டா ஜநரல் ,மால்டா ,நாதுர் ,கமினோ ,கால ,மால்டிஸ் ,மரியா க்ரஸிய காசர் ,ஃப்ரெட்ரிக் அஸ்ஸ்ஒப்பர்டி ,மிஜ்ஜி ஆர்கநைஸேஶந் ,மால்டா கோஸோ சரி செய்யப்பட்டது இணைப்பு ,மால்டா கோஸோ கூட்டமைப்பு ,உள்கட்டமைப்பு மால்டா ,கோஸோ கூட்டமைப்பு ,ஆல்பர்ட்டா தீ ,க்ரஸிய காசர் ,கோஸோ சேனல் ,ஒப்பந்தங்கள் துறை ,

© 2025 Vimarsana