Cost overruns on the Keeyask and Bipole III projects by Manitoba Hydro were caused by a combination of incomplete planning and lack of oversight by the Selinger government, according to the results of an economic review released by the Manitoba Government on Friday.
Advertisement
Cost overruns on the Keeyask and Bipole III projects by Manitoba Hydro were caused by a combination of incomplete planning and lack of oversight by the Selinger government, according to the results of an economic review released by the Manitoba Government on Friday.
The commission handling the report was run by former Saskatchewan premier Brad Wall, who was tasked with looking into the cause of the projects costing a combined $13.4 billion when initial spending estimates had pegged the cost as being approximately $9.7 billion.