The district has $330,000 of an allowance.
The second change order was to add items such as signage and upgrade its storm shelter based on peer reviews for a total of $194,230.28.
This happens when builders continue to build the school and find things that were not taken into consideration.
"Project is well underbudget, we're at about 11% on an $84 million  budget," said Sean Lehman, consultant for Hillsdale.
OTHER BUSINESS  
The board recognized the retirement of two district employees: Karen Cook (playground aid, 26 years at Hillsdale Elementary School) and Frances Howman (custodian, over 50 years in the district).
The board approved a property transfer from Hillsdale Local Schools to Northwestern Local Schools. The property is 1639 Township Road 65, Jeromesville. There is no set date yet. The family members in the house all went to Northwestern, however they live within the Hillsdale line.

Related Keywords

Karen Cook ,Sean Lehman ,Christine Jenkinson Ashland ,Frances Howman ,Hillsdale School Board ,Hillsdale High School ,Hillsdale Elementary School ,Ashland Times ,Local Schools Board ,Hillsdale Board ,Hillsdale Local Schools ,Northwestern Local ,House Bill ,கரேன் சமைக்கவும் ,சீன் லெஹ்மன் ,கிறிஸ்டின் ஜென்கின்சன் ஆஷ்லேண்ட் ,ஹில்ஸ்டேல் உயர் பள்ளி ,ஹில்ஸ்டேல் தொடக்க பள்ளி ,ஆஷ்லேண்ட் முறை ,உள்ளூர் பள்ளிகள் பலகை ,ஹில்ஸ்டேல் பலகை ,ஹில்ஸ்டேல் உள்ளூர் பள்ளிகள் ,வடமேற்கு உள்ளூர் ,வீடு ர சி து ,

© 2025 Vimarsana

comparemela.com © 2020. All Rights Reserved.